Phase 2 membrane project, Day 105–November 26, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 12°C, heavy rain with late clearing, clouds
Workers onsite: At least 5

Work done today:

  • Concrete brick placed for the garden area adjacent to the Building 240 entrance and alongside initial part of the sidewalk on the north side of the Visitor Parking
  • Additional compacting of gravel and placing of pavers around the 240 entrance
  • Building 240 entrance re-opened, with temporary path to driveway