Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 13°C, mostly sunny
Workers onsite: At least 3
Work done today:
- Remainder of exposed concrete slab has been ground/polished
- Initial layer of sealant has been applied to a large portion of the area