Phase 2 membrane project, Day 67 and 68–October 9/10, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: Around 13–15°C, mostly sunny
Workers onsite: At least 3

I’ve been busy the past few days so I’m combining the work done on Friday and Saturday into one post.

Work done:

  • Some more pavers installed in the parking lot
  • Additional compacting of gravel in the area in front of the 240 building (Saturday)
  • Some minor housekeeping (cleaning, organization)

It’s possible other work may have been done, but I did not observe anything specific.