Phase 2 membrane project, Day 66–October 8, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 21°C, mostly sunny
Workers onsite: At least 8

Work done today:

  • Additional extension of pavers in the parking lot adjacent to Building 244
  • Filter fabric placed alongside Building 240’s east edge in preparation for reinstatement of sidewalk
  • Trench drain ends were dug out for inspection. This is to prepare for its replacement or possible refurbishment. The holes were filled after the inspection was complete.