Phase 2 membrane project, Day 60–October 1, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 16°C, cloudy, early showers
Workers onsite: At least 6

Work done today:

  • More compacting of the gravel, particularly adjacent to Building 240