Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 15°C, cloudy, some showers
Workers onsite: At least 6
Work done today:
- Further extension of aggregate (gravel) on drainage mat adjacent to Building 240
- Additional layer and compacting of gravel adjacent to Building 244