Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 28°C, sunny
Workers onsite: At least three
Work done today:
- Two of the Building 240 patios had membrane applied
- Sealant was applied to two other patios
- The last patio has not been worked on yet