Phase 2 membrane project, Day 13–August 4, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: February 2027 (new, was December 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 29°C, sunny with smoke haze
Workers onsite: At least seven

Work done today:

  • Sealant applied to most of the newly exposed concrete slab in the visitor parking adjacent to Building 244
  • Membrane installation continuing in the same general area
  • Initial work on the next set of patios, including removal of some Hardie planking