Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 29°C, sunny with smoke haze
Workers onsite: At least seven
Work done today:
- Completion of application of sealant and membrane in the recently cleared concrete slab adjacent to Building 244.
- Closure of access to Allen Street, except via fire door in Building 240, to allow for further membrane installation.
Notes:
- The closure of pedestrian access to Allen Street is expected to last one week, per Prostar. As the closure and notice of the closure were given the same day, it was not possible to get advance word out to owners and other residents.