Phase 1 Membrane Project, Day 122 (January 31, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 11C, rain and cloud

Work done today:

  • Affected patios and wooden beam were power-washed and all construction material removed
  • Down spouts were put back in place
  • Pavers for the sidewalk leading to the staircase have been extended farther out toward the parking lot
  • Additional Allan blocks have been placed alongside the pavers, with capping stones on top
  • The first tier of the retaining wall behind the 244 building has been cleaned, with construction materials removed
  • Workers onsite: At least four