Phase 1 Membrane Project, Day 80 (December 4, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 7C, rain

No work onsite today.

NOTE: I believe Prostar is waiting for some updated design work from Strata Engineering before continuing, which means we may not see anyone on site, except possibly for inspections, until Monday, December 8th.