Phase 1 Membrane Project, Day 79 (December 3, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 6C, mix of clouds and showers

Work done today:

  • Additional work on the membrane between the 244 and 248 buildings
  • Workers onsite: Observed at least 1