Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 6C, mix of clouds and showers
Work done today:
- Additional work on the membrane between the 244 and 248 buildings
- Workers onsite: Observed at least 1