Phase 1 Membrane Project, Day 78 (December 2, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 7C, mix of sun and cloud

No work onsite today.

Prostar is apparently awaiting a Field Report from Strata Engineering to resume specific work. The patios are estimated to be 95% complete at this stage.