Phase 2 membrane project, Day 1 – July 20, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 31°C, mostly sunny
Workers onsite: 6–8, varying at times

Work done today:

  • Entire south side of visitor parking lot fenced off
  • Pavers removed from south sidewalk adjacent to Building 244
  • Start of demolition of four patios in Building 244 for membrane replacement
  • Allan blocks removed from remaining planter outside Building 244
  • Two down spouts fitted to Building 240 in the emergency repair area

A few observations:

  • The majority of the closed-off parking area is not being used and the loop around is again cut off. This severely restricts the number of parking spaces and may hinder access by emergency vehicles.
  • I have already observed people parking in any free space.
  • No work in the Phase 1 extension or emergency repair area (except the down spouts being attached as noted above). Unclear when these areas will be done, with the project now expanding into Stage 3.