Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 11C, rain and cloud
Work done today:
- Affected patios and wooden beam were power-washed and all construction material removed
- Down spouts were put back in place
- Pavers for the sidewalk leading to the staircase have been extended farther out toward the parking lot
- Additional Allan blocks have been placed alongside the pavers, with capping stones on top
- The first tier of the retaining wall behind the 244 building has been cleaned, with construction materials removed
- Workers onsite: At least four