Phase 1 Membrane Project, Day 77 (December 1, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 6C, clouds and intermittent showers in the afternoon

The biweekly onsite meeting took place with:

  • Strata Engineering
  • Prostar
  • Copperstone Council, represented by the Vice President
  • Quay Pacific had no representation (no reason given)

Prostar updated on plans moving forward:

  • They hope to have the patios finished before the Christmas break.
  • They hope to have some soil put back before the Christmas break.
  • Work will continue until December 22, then resume on January 2, 2026.

Work done today:

  • More work on completing installation of membrane on the five affected patios.
  • Workers onsite: At least four.