Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 9C, cloudy
Work done today:
- Continued work on installing membrane on the five affected patios.
- Application of primary to the majority of the concrete slab between the 244 and 248 buildings.