Phase 1 Membrane Project, Day 66 (November 18, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 9C, cloudy

Work done today:

  • Continued work on installing membrane on the five affected patios.
  • Application of primary to the majority of the concrete slab between the 244 and 248 buildings.