Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 10C, clouds and showers
Work done today:
- Additional repair work on leaks
- Delivery of two large propane tanks
- Delivery of at least five large cans of liquid material (possibly primer)
- Workers on site: At least 3