Phase 1 Membrane Project, Day 40 (October 18, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/

Weather: 12C, rain

Work done today:

  • Power-washing to remove remaining membrane material (residue) continued.
  • Stucco removed from along the base of 244 building in the space between 244 and 248 buildings and the west side of the 244 building adjacent to the hospital.
  • Small section of stone cladding removed from the 244 building (see photo below) in preparation for the required eight-inch overlap of new membrane material that will extend up higher than the previous membrane.
  • Workers onsite: Observed at least four.

Leave a Comment