Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
Weather: 12C, rain and cloudy conditions
A rare day of work on a Saturday!
Work done today:
- Plumbing and piping installed for the three new drains drilled yesterday.
- Workers onsite: Two
In theory, the project should be very close or ready for the installation of the new membrane material.