Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 12C, rain and cloudy conditions
A rare day of work on a Saturday!
Work done today:
- Plumbing and piping installed for the three new drains drilled yesterday.
- Workers onsite: Two
In theory, the project should be very close or ready for the installation of the new membrane material.