Phase 1 Membrane Project, Day 35 (October 10, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 14C, rain

Work done today:

  • Three new drains cored/drilled in the area between the 244 and 248 buildings:
    • The first drain is near the edge of the parking lot
    • The second drain is about midway to the steel staircase, just off of where the pathway normally is
    • The third is adjacent to the steel staircase, closer to the 248 building
  • Workers onsite: Observed two, possibly more

The three drains: