Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 14C, rain
Work done today:
- Three new drains cored/drilled in the area between the 244 and 248 buildings:
- The first drain is near the edge of the parking lot
- The second drain is about midway to the steel staircase, just off of where the pathway normally is
- The third is adjacent to the steel staircase, closer to the 248 building
- Workers onsite: Observed two, possibly more
The three drains: