Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 18C, rain in morning, sun and cloud in afternoon
Work done today:
- More removal of membrane from construction area
- Removal of bottom stairs on the steel staircase between the 244 and 248 buildings (presumably to keep people from using them–this will be even more important once the new membrane starts getting laid down)
- Additional clean-up of the area
- Workers onsite: 3-5