Phase 1 Membrane Project, Day 28 (October 2, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 17C, sun and cloud

Work done (first work since September 19th):

  • First three patios had membrane removed
  • Partial removal of membrane in area between 244 and 248 buildings
  • Workers onsite: Observed 3, possibly more

Leave a Comment