Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
Weather: 23C, sun and cloud mix
Work done today:
- The ground surface behind the 244 building was hosed down.
- All trees, bushes and other vegetation from between the 244 and 248 buildings were removed.
- Wooden beams alongside the 248 building were removed.
- Additional Allan blocks have been temporarily stored in the central courtyard (visitor parking).