Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 10C, rain and cloud
Work done today:
Topsoil distributed over the majority of the worksite
Workers onsite today: Six
Workers spreading soil in the area between the 244 and 248 buildings
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 9C, rain
Work done today:
Some drains have been covered with a root barrier cloth
Concrete curb has been covered with material to prevent water/debris getting into the soil that will sit over top of it
Sand/light soil has been applied to most of the area behind the 244 building, to just below the piping for the irrigation system. This will form the base layer on which the soil will be placed.
Gravel has been filled in around the ventilation shaft at the corner of the 244 building
Some of the Allan blocks around the ventilation shaft have been restored
Workers onsite today: Four
The shot below shows the following, from top to bottom:
Allan block wall adjacent to hospital lane
Concrete curb covered in protective material
Main area that will be lawn, now filled with sand/light soil, drainage piping partly exposed
Drain with root barrier cloth covering it to prevent soil from getting into the piping below
Wooden beam running around the back of the 244 building
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 11C, cloudy
Work done today:
Stone (gravel) was placed around the ventilation shaft by the 244 building, and an aeration mat was also put in place, though it may not be resting on clean material (this may change, possibly)
Perforated pipes were extended out of drains where soil will be placed, to facilitate proper drainage through the soil
Additional Allan blocks were put in place
The aeration mat has been taped down in more areas
A load of sand/light soil was delivered. This will be the base layer for the soil.
Workers onsite: Four
Small excavator next to the load of sand that was delivered today.One of the drains with perforated piping added.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 5C, cloudy
Work done today:
Mastick (sealant) material applied to the sides of the ventilation shaft at the northwest corner of the 244 building, in preparation for gravel and overburden (soil) being placed.
Workers onsite: At least two.
Mastick material (black) applied to ventilation shaft. Also visible is the new irrigation piping.
Today was also the biweekly meeting between all parties:
Strata Engineering
Prostar
Copperstone Council (represented by the Vice President)
Quay Pacific
A report on current work will be sent from council to owners soon.
NOTE: At today's meeting, Prostar claimed their absence over most of the previous week was to allow the irrigation team to complete their work.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 6C, sunny
Work done today:
Completion of the gravel being reinstated between the 244 building and wooden beams
Continued work on pavers for sidewalk leading to the metal staircase
Additional extension of Allan blocks that will form the two planters between the 244 and 248 buildings
Additional fit and finish work on patio pavers
Workers onsite: Four
Wooden planks used to carry gravel in a wheelbarrow to the area behind the 244 building.Gravel in place.
Project Mobilization Date: August 11, 2025 Work Start Date: August 28, 2025 Expected duration: 2–3 months (Completion now likely in February 2026) Primary contractor: Prostar https://prostar.ca/
Weather: 8C, sunny
Work today:
Gravel is being moved in place between the 244 building and wooden beams