Phase 1 Membrane Project, Day 28 (October 2, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 17C, sun and cloud

Work done (first work since September 19th):

  • First three patios had membrane removed
  • Partial removal of membrane in area between 244 and 248 buildings
  • Workers onsite: Observed 3, possibly more

Phase 1 Membrane Project, Day 27 (October 1, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 17C, rain throughout day, some cloud breaks

No work onsite today.

Phase 1 Membrane Project, Day 26 (September 29, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 16C, rain

No work onsite today.

Phase 1 Membrane Project, Day 25 (September 27, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 18C, cloudy, showers in early morning

No work onsite today.

NOTE: Currently work is not being done on Saturdays, though under city permit, it is allowed. I am including Saturdays to avoid confusion about what is happening on those days.

Phase 1 Membrane Project, Day 24 (September 26, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 18C, showers in morning, sun and cloud after

No work onsite today.

Phase 1 Membrane Project, Day 23 (September 25, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 21C, mix of sun and cloud

No work onsite today.