Phase 1 Membrane Project, Day 8 (August 19, 2025)

August 21, 2025August 19, 2025 by Stan
Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

No activity onsite today.

Categories Membrane Project, Phase 1 Leave a comment

Phase 1 Membrane Project, Day 7 (August 18, 2025)

August 19, 2025August 18, 2025 by Stan
Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather today: Cloudy with some sun.

No activity onsite today.

Categories Membrane Project, Phase 1 Leave a comment

Phase 1 Membrane Project, Day 6 (August 16, 2025)

August 17, 2025August 16, 2025 by Stan
Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather today: Rain in the morning, sun and cloud in the afternoon.

No activity onsite today.

Categories Membrane Project, Phase 1 Leave a comment

Phase 1 Membrane Project, Day 5 (August 15, 2025)

August 16, 2025August 15, 2025 by Stan
Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather today: Heavy rain

No activity onsite today.

Categories Membrane Project, Phase 1 Leave a comment

Phase 1 Membrane Project, Day 4 (August 14, 2025)

August 15, 2025August 14, 2025 by Stan
Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

No observable activity today. I suspect they may be waiting on permits from the City of New Westminster.

Categories Membrane Project, Phase 1 Leave a comment

Phase 1 Membrane Project, Day 3 (August 13, 2025)

August 13, 2025 by Stan
Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

I observed someone working on and in the C container, but no further work on the property was done today that I could see.

Categories Membrane Project, Phase 1 Leave a comment
Older posts
Newer posts
← Previous Page1 … Page15 Page16 Page17 Next →

Issues and Ideas

  • A positive future for Copperstone

Official Community newsletters

  • July 2025 (PDF)
  • May 2025 (PDF)
  • April 2025 (PDF)

Resources

  • BC Strata Property Act
  • BC Strata Housing
  • CHOA
  • Stratawatch
  • Civil Resolution Tribunal
  • City of New Westminster

Forum

  • Copperstone Community Forum

Latest Posts

  • Phase 1 Membrane Project, Day 84 (December 9, 2025)
  • Phase 1 Membrane Project, Day 83 (December 8, 2025)
  • Phase 1 Membrane Project, Day 82 (December 6, 2025)
  • Phase 1 Membrane Project, Day 81 (December 5, 2025)
  • Phase 1 Membrane Project, Day 80 (December 4, 2025)