Phase 1 Membrane Project, Day 72 (November 25, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 6C, rain and clouds

Work done today:

  • A single worker was observed shovelling debris into the trash bin next to the worksite.

Phase 1 Membrane Project, Day 71 (November 24, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 7C, rain

Work done today:

  • Additional membrane was applied on several patios
  • Workers observed: At least three

Phase 1 Membrane Project, Day 70 (November 22, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 11C, steady rain most of the day

No work onsite today.

Phase 1 Membrane Project, Day 69 (November 21, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 8C, rain, occasional breaks

No work done today.

It is unclear why no one was onsite today, as it is a regular workday and there is much work still to be done before the project can be completed.

The following photos were taken today, November 21, 2025.

Phase 1 Membrane Project, Day 68 (November 20, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 9C, cloudy

Work done today:

  • Continued work on the membrane installation between the 244 and 248 buildings.
  • Workers onsite: At least four.

Phase 1 Membrane Project, Day 67 (November 19, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 11C, some clearing, cloudy

Work done today:

  • The first layer of membrane was applied to the concrete slab between the 244 and 248 buildings
  • The area behind the 244 building was further cleaned/cleared, primarily using a leaf blower
  • Strata Engineering was onsite, others may have been as well
  • Workers onsite: At least two observed

View from hospital path showing the first layer of membrane on the concrete slab bwtween the two buildings: