Phase 1 Membrane Project, Day 51 (October 30, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 13C, sun, with some clouds

Work done today:

  • Remainder of wood forms for concrete curb placed, specifically behind and around the staircase.
  • Concrete slab prepared along edge of 248 building for new membrane, with Kryten material applied.
  • Workers onsite: At least two observed.