Phase 1 Membrane Project, Day 50 (October 29, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 14C, mix of sun and cloud

Work done today:

  • Cleaning of concrete slab and further removal of debris.
  • Placement of the wood framing for the concrete curb to be installed along the retaining wall behind the 244 building.
  • A replacement drain cored on the concrete slab between the 244 and 248 buildings to replace one that was drilled in a suboptimal location.
  • Removal of lumber from the back of the 244 building to the central courtyard.
  • Arrows spray-painted onto the concrete slabs to indicate cracks or other defects in the concrete.
  • Emergency mastic applied to a duct on the concrete slab behind the 244 building, as membrane removal had resulted in water flowing into the ducting and down into a fan/heater in the underground parkade. This will be removed when the new membrane is applied.
  • Workers onsite: At least four observed.