Phase 1 Membrane Project, Day 47 (October 25, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 10C, rain, gusting wind at times, clouds

Work done today:

  • Shot blasting of the exposed portion beneath the Allan block wall behind the 244 building, in preparation for the concrete curb that will go in the same area.
  • Workers onsite: At least four observed.

Shot blasting material used was Enviro-Grit Abrasives Enviro-Grit. The product page is here: https://www.enviro-corp.ca/enviro-grit. It’s basically extra fine glass dust.

The photo below was taken from our patio.

NOTE: The work crew was still here at 8 p.m., which appears to be a violation of New Westminster City Bylaw 8013, part of City Bylaw 6063 (Construction Noise):

Bylaw 6063 can be viewed as a PDF here: https://www.newwestcity.ca/database/files/library/Consolidated_Bylaw_6063__1992_Construction_Noise(1).pdf