Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
Weather: 12C, cloudy, some showers
Work done today:
- Continued removal of membrane residue between the 244 and 248 buildings and along the back (west) side of the 244 building.
- Work expanded to patios, with all but one patio in various states of having all membrane residue removed.
- Workers observed: At least three.
Additional work to be done before new membrane can be installed (incomplete list):
- Removal of lowest planking on the back of the 244 building, to allow expanded membrane coverage.
- Removal of lower portion of stone cladding through same area as above (you can see an example of this removal in the first photo below).
- Blasting of both of the above exposed surface areas, to allow clean installation of new membrane.
- Additional membrane residue removal along edges in various areas.