Phase 1 Membrane Project, Day 43 (October 22, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/

Weather: 12C, cloudy, some showers

Work done today:

  • Continued removal of membrane residue between the 244 and 248 buildings and along the back (west) side of the 244 building.
  • Work expanded to patios, with all but one patio in various states of having all membrane residue removed.
  • Workers observed: At least three.

Additional work to be done before new membrane can be installed (incomplete list):

  • Removal of lowest planking on the back of the 244 building, to allow expanded membrane coverage.
  • Removal of lower portion of stone cladding through same area as above (you can see an example of this removal in the first photo below).
  • Blasting of both of the above exposed surface areas, to allow clean installation of new membrane.
  • Additional membrane residue removal along edges in various areas.