Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 14C, mix of sun, cloud and showers
Work onsite today:
- Continued removal of membrane material from between buildings 244 and 248, as well as along the west side of the 244 building.
- Workers onsite: 3 observed.