Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 14C, sunny, some clouds
Work done today:
- Continued removal of membrane (apparently using a power washer of some type).
- Removal of stone cladding along bottom edge of building in preparation for extended membrane application, using a hammer and chisel.
- Workers onsite: At least 2 observed