Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/
Correction: This post originally identified the people onsite as likely from Prostar. This has been changed, as it was likely Strata Engineering onsite.
Weather: 15C, clouds and sun
Work done today:
- Two people observed doing inspection of work area, likely from Strata Engineering, as they do inspections prior to the biweekly status meetings.
- Workers onsite: 2, possibly more.