Phase 1 Membrane Project Day 33 (October 8, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 15C, cloudy

Work done today:

  • Continued work on stripping the membrane from behind the 244 building
  • Workers onsite: 3-5

More photos of the area coming soon!