Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/
Weather: 17C, sun and cloud
Work done today:
- Continued stripping of membrane behind the 244 building using the Terminator (yes, that is what the machine is called)
- Workers onsite: 3-5

