Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now expected in January 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 21C, sunny
No work done onsite today. The second bi-weekly status meeting took place involving:
- Copperstone Council (Vice President attending)
- Prostar
- Strata Engineering
- Sub contractor reps
Review of the previous two weeks took place, as well as discussion on moving ahead on specific parts of the project.