Phase 1 Membrane Project, Day 2 (August 29, 2025)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months
Primary contractor: Prostar https://prostar.ca/

Weather: Sunny, 29°C

NOTE: The stairway to the hospital path is closed as of today, and is likely to not re-open until the project is complete.

Work today:

  • The back area of the 244 building has been hosed down and further cleared.
  • A small excavator was brought in to begin removing the dirt from behind the 244 building and the stretch of lawn between the 244 and 248 buildings. It was onsite until around 4 p.m.
  • The dirt was loaded into a dump truck and removed from the complex.
  • Some of the stone work around the stretch of lawn between 244 and 248 has been dismantled and is being stored in the central courtyard.

A few more previously buried drains behind and beside the 244 building have been exposed.