Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Day 2 saw actual work begin:
- The C container arrived and was set up on the central courtyard
- A subcontractor to Prostar began and completed most of the sod removal behind and along the south side of the 244 building




