Phase 2 Membrane Replacement Project
Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering
Weather: 11°C, mostly sunny
Workers onsite: At least 6
Work done today:
- Continued stripping of entrance area of Building 240 in preparation for application of sealant and membrane
- Reinstatement of more pavers around the central courtyard
- The first of two days coring new drains that will provide better overall drainage in the parking lot