Phase 2 membrane project, Day 87–November 4, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 12°C, mostly cloudy
Workers onsite: At least 8

Work done today:

  • Continued work on applying second layer of membrane to area near to Building 240

(No photos for this day.)