Phase 2 membrane project, Day 64–October 6, 2026

Phase 2 Membrane Replacement Project

Project Mobilization Date: July 20, 2026
Work Start Date: May 4, 2026 (for emergency repairs)
Expected completion: December 2026
Primary contractor: Prostar
Engineering design: Strata Engineering

Weather: 21°C, mostly sunny
Workers onsite: At least 9

Work done today:

  • Blue Drop continued installing new irrigation piping
  • Additional drainage mat and wooden beams installed along perimeter of Buildings 240 and 244
  • More compacting of gravel throughout work area
  • Removal of old, more finely ground gravel from Phase 1 extension area. This will be replaced by the newer aggregate material approved by Strata Engineering.
  • A small section of pavers has been reinstalled in the parking lot adjacent to Building 244