Emergency membrane repair (pre-Phase 2 work), Day 4

Weather: 20°C, partly sunny
Workers onsite: At least three

Work done today:

  • Most of the work was preparation for additional repairs that will be done around patios and the concrete slab between Building 240 and 244.
  • The protective fencing is mostly complete now extends around the Heritage Courtyard trees and the tree on the west side of the entrance to the property on Sherbrooke Street.

REMINDER: The gates in the fencing are to allow for watering of the trees and to allow passage through to either side of the courtyard. It’s a violation of a New Westminster bylaw to actually stay inside the protected area (unless you’re a squirrel).

Membrane is expected to arrive onsite tomorrow (Friday).