Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 13C, sunny
No work onsite today.
The next meeting of all parties is on Monday, February 9, 2026. Depending on what comes out of the meeting, I will likely stop daily updates on Phase 1 and only update when there is new activity or relevant news to share.