Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/
Weather: 5C, cloudy
Work done today:
- Mastick (sealant) material applied to the sides of the ventilation shaft at the northwest corner of the 244 building, in preparation for gravel and overburden (soil) being placed.
- Workers onsite: At least two.

the new irrigation piping.
Today was also the biweekly meeting between all parties:
- Strata Engineering
- Prostar
- Copperstone Council (represented by the Vice President)
- Quay Pacific
A report on current work will be sent from council to owners soon.
NOTE: At today's meeting, Prostar claimed their absence over most of the previous week was to allow the irrigation team to complete their work.