Phase 1 Membrane Replacement Project
Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/
Weather: 6C, sunny
Work done today:
- Completion of the gravel being reinstated between the 244 building and wooden beams
- Continued work on pavers for sidewalk leading to the metal staircase
- Additional extension of Allan blocks that will form the two planters between the 244 and 248 buildings
- Additional fit and finish work on patio pavers
- Workers onsite: Four