Phase 1 Membrane Project, Day 115 (January 22, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 6C, mostly cloudy

No work onsite today.

Prostar management was looking at the work area today. I am unsure if all four people were from Prostar or if some may have been contractors or from Strata Engineering.