Phase 1 Membrane Project, Day 106 (January 12, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion now likely in February 2026)
Primary contractor: Prostar https://prostar.ca/

Weather: 9C, rain

Work done today:

  • Remediation work to address deficiencies began today. This covers the root barrier, aeration mat, certain materials and more.
  • Work began on assembling the double stack of wooden beams between the 244 and 248 buildings.
  • The biweekly meeting took place onsite, with representatives of the following attending:
    • Strata Engineering
    • Prostar
    • Copperstone Council (represented by the Vice President)
    • Supervisor for Prostar workers
  • Initial setup on the replacement irrigation system began with a separate contractor, mostly staging equipment and material.

Leave a Comment