Phase 1 Membrane Project, Day 103 (January 8, 2026)

Phase 1 Membrane Replacement Project

Project Mobilization Date: August 11, 2025
Work Start Date: August 28, 2025
Expected duration: 2–3 months (Completion TBD)
Owner updates: Phase 1 Membrane Project Official Updates
Calendar of days worked: August 2025 to February 2026
Primary contractor: Prostar https://prostar.ca/

Weather: 5C, cloudy

Work done today:

  • Continued work on cutting and placing the wooden beams around the base of the 244 building.
  • Workers onsite: At least two.